OCTOFER

Rolling stock maintenance

Night-time conversion works in the Catogne hall

Entry into service in 2026

TMR has been selected to maintain RegionAlps' future FLIRT Evo trainsets, built by Stadler. To carry out this assignment, the Catogne hall — located behind the Octofer bogie overhaul centre — will be converted.

Connected directly to Martigny SBB station, this new maintenance centre sits on the Simplon line. It therefore enjoys a strategic and easily accessible location.

With this project, TMR reaffirms its commitment to strengthening its activities and its leading role in rail expertise: bogie overhaul, maintenance and engineering.

3D view of the FLIRT Evo trainsets inside the maintenance hall

Our objective

Our objective is to welcome the first FLIRT Evo trainsets in summer 2025; construction started this summer. The first years of operation will allow us to build up a structure that should, by 2030, employ around 25 full-time staff maintaining several dozen vehicles each year.

The maintenance contract for RegionAlps' FLIRT Evo trainsets represents roughly 50 % of the hall's capacity. Thanks to the bogie workshop housed in the same building, valuable synergies can be offered to our customers.

3D views

  • Entrance – rooftop access walkways

    Entrance – rooftop access walkways

  • Overhead travelling crane

    Overhead travelling crane

  • Underfloor wheel lathe

    Underfloor wheel lathe

  • Bogie exchange installation

    Bogie exchange installation

Outlook

Planned works

The following works are planned in order to host the maintenance of RegionAlps' FLIRT Evo trainsets:

Construction machinery inside the Catogne hall under conversion
  • Creation of 3 pit tracks 100 m long (tracks 93 to 95).

  • Construction of a new steel structure to carry the access walkways and overhead cranes, notably over 2 tracks.

  • Construction of a large pit in track 93 to house an underfloor wheel lathe and its setting track.

  • Rehabilitation of a 100-metre outdoor track extending the wheel lathe, allowing multiple units up to 205 metres long to be reprofiled.

  • Construction of a very large "crossing" to house a lifting table for exchanging bogies or major components, optimising maintenance operations.

  • 2 levelled tracks will allow various adjustments to be carried out in line with the applicable standards.

Follow the progress of our building sites

21 August 2024 marked the start of the conversion works in the Catogne hall. Follow the progress in pictures, and discover all our rail infrastructure projects on the TMR Infra website.

Illustration of a TMR rail construction site